Downtown Culver City Outdoor Dining Expansion Project

  • Project TypeSidewalk Improvements
  • Project ScheduleFebruary 2022 - March 2022
  • Contractor nameMMJ Contracting, Inc.
  • Completion DateMarch 31, 2022
downtown dining 5.png

Project Description

On January 24, 2022  the City Council approved the Downtown Outdoor Space Expansion Project to provide increased, flexible outdoor areas for existing and future businesses. The project area encompasses four blocks on the east side of Culver Boulevard from Duquesne Avenue to Canfield Avenue. The general scope of the project focuses of the removal of large, in-ground planters, installation of new paving treatments, and upgrading furnishings. 

Construction will result in loss of temporary outdoor dining spaces, a brief loss of driveway access to property along the route, and construction noise, dust, etc. even though every effort will be made by the City and the Contractor to minimize these inconveniences.

Construction Schedule

  • Commence: February 7, 2022 
  • Complete: March 31, 2022 (anticipated)
  • Expected Work Hours: 8:00 AM to 5:00 PM Monday - Friday (with break from loud construction noise and debris 11:30 AM – 1:30 PM)
  • Construction sequencing is scheduled block by block 
  • Work will begin on the north side of Culver Boulevard on the block between Cardiff Avenue and Main Street

Construction Sequence

  • Cardiff Avenue – Main Street: February 9th – February 24th
  • Duquesne Avenue – Washington Boulevard: February 15th –  March 8th (may be extended a few days if necessary)
  • Main Street – Canfield Avenue: February 24th – March 11th
  • Watseka Avenue – Cardiff Avenue: March 8th –March 30th

Learn More

Location

Downtown Culver City - East Culver Boulevard between Duquesne Avenue and Canfield Avenue,    View Map